SPECIAL FOCUS >> RISING CONSTRUCTION COSTS
Stories from the Front
Three developers use savvy
strategies to keep their deals alive
BY BENDIX ANDERSON
AFFORDABLE HOUSING FINANCE • OCTOBER 2007
When Hurricane
Katrina knocked
down trees and cut
electrical power to
Meridian, Miss.,
Michaels Development Co. was just
preparing to negotiate contracts and
lock in construction costs for J.T. Davis
Court, the first phase of a HOPE VI
redevelopment of the public housing
project there called Victory Village.
But the cost of labor and construction
materials immediately began to
rise throughout the Gulf Coast.
Michaels had just a few months to close
a $300,000 gap in its construction
budget in time to close on a tax-exempt
bond-backed mortgage for the 76,000-
square-foot project, which would cost
$9.8 million to develop, with a hard
construction cost of $6.3 million, or
$83 per square foot.
Michaels was helped by its habit of
bringing experts into the design
process early, even though the HOPE
VI program urges developers to extend
the bidding process and wait to hire
general contractors until shortly before
the project’s financing closes. With the
general contractor already chosen,
Michaels began to cut costs.
“We were going through every page
of the [construction] documents in
order to get the numbers down,” said
Jim Miller, vice president for Michaels.
The company saved $140,000 in
site work by closely reviewing the geotechnical
engineer’s report. Some of the
soil under the project site was wet and
had to be replaced with dry soil for the
72-unit development’s foundation—but
the development didn’t need nearly as
much dry soil as the engineer had specified.
If the general contractor had
joined the team later, it might have
been impossible to make the change
and recoup the savings, said Miller.
The contractor also suggested
switching from copper piping to much
less expensive Pex, a type of flexible
plastic piping. The cost of copper was
already rising fast, and the change
saved the project $30,000. Ditching
copper also helped J.T. Davis avoid the
break-ins suffered by other area developers
who stored copper on their sites.
“No one’s going to come in and steal the
Pex,” said Miller.
The contractor also suggested
going from a three-step painting
process to a two-step process recommended
by the paint manufacturer that
saved $23,000. Switching Kohler and
Moen plumbing fixtures for less expensive
“builder grade” fixtures also saved
the development $6,000.
Thanks to its more than 20 years
in the business, Michaels has the knowhow
to close budget gaps fast, although
the developer has never had to contend
with a gap that grew as fast as the one
that resulted from Hurricane Katrina.
Last-minute cuts
save Evergreen Vista
When rising construction costs
carved a $1.5 million hole in the budget
to develop Evergreen Vista II, an
affordable housing project in Olympia,
Wash., Mercy Housing had to dramatically
scale back its plans for the 50-unit
community.
Mercy, a nonprofit affordable
housing developer based in Denver,
closed roughly $450,000 of the gap
simply by negotiating with contractors
and pushing for lower bids.
The nonprofit cut another
$450,000 by poring over details of the
project’s design and construction to
find any expense that could be
trimmed. It was a painful process, said
Walter Zisette, vice president for
Mercy.
Eliminating a playground from the
project saved more than $60,000. The
nonprofit developer also shrank 100
bedrooms from 10 feet by 12 feet to 10-
by-10, saving $100,000. And Mercy
removed 1,200 square feet of office
space and cut back on landscaping
details like trellised gateways.
All those cuts still left a $600,000
hole in Evergreen’s budget, which had
to be filled with new capital. Mercy
started by deferring $310,000 of its
own $400,000 developer fee. The nonprofit
also raised an extra $260,000
from foundations, including the Bill &
Melinda Gates Foundation. Plus, city
and state subsidy programs contributed
more financing. “We went back to every
funder and asked them to share the
pain,” Zisette said.
Finally, Mercy balanced
Evergreen’s $9.7 million total development
budget. The hard cost of construction
for the 51,000-square-foot
project came to $6.1 million, or $120
per square foot. Construction started in
October 2006 and is slated to finish
this year.
Stalling for time
In 2005, Simpson Housing
Solutions had four projects that ran
over their budgets by 15 percent as construction
costs swelled, a gap totaling
more than $4 million. Simpson solved
the problem by talking its general contractors
into accepting notes from
Simpson—effectively IOUs—to cover as
much as half of the construction cost
overruns, or an average of about
$450,000 apiece.
For example, when rising costs
pushed the Villa Monterey Apartments,
a 9 percent low-income housing tax
credit project in Blythe, Calif., almost
$1.5 million over its construction budget,
the general contractor accepted a
note from Simpson to cover nearly
$400,000 of the overrun. Otherwise,
the deal would have collapsed, and the
contractor, which had worked with
Simpson on several other deals, would
have lost the job.
The note will be paid, with interest,
from Villa Monterey cash flow.
Simpson, an affordable housing developer
based in Long Beach, Calif., also
deferred all but $100,000 of its $1.2
million developer fee for the $11.9 million
project. The hard cost of construction
for the 104,000-square-foot development
came to $7.8 million, or $75
per square foot.
So Simpson, a for-profit developer,
has surrendered most of the income
from Villa Monterey. “It’s a pain, but we
needed to get these communities done,”
said Moe Mohanna, senior vice president
for Simpson.
|