PARTING SHOTS
APARTMENT FINANCE TODAY • NOVEMBER/DECEMBER 2007
Hard Construction Lessons
G&D Developers finished the first phase of its Regatta
development this year and is working on the $57 million
second phase with its partner, the Weintraub Cos.
By Bendix Anderson
Miami Beach, Fla.—After
months of delays, expensive
changes to construction
plans, and an acrimonious
lawsuit against the general
contractor on its Regatta
condominium development
here, G&D Developers
vowed not to repeat its mistakes.
The 52 condominiums in Regatta’s
first phase were finished this February at
a total development cost of $33 million.
That includes $25 million in hard construction
costs. At $180 per square foot,
the hard cost was $40 per square foot
more than G&D had expected to pay.
Although sales made up for the extra
costs, bringing in an average $100 per
square foot more than the developer’s
pro forma estimate of $350, the company
resolved to keep construction costs
under control in Regatta’s second phase
by giving its next general contractor a
stake in the development.
This time around, G&D chose a general
contractor with whom the developer
has successfully worked with before:
Avi Weintraub, founder of the
Weintraub Cos. G&D made Weintraub
a co-developer, a role that came with an
equity stake in the development and a
powerful incentive to maximize profits.
Weintraub found ways to trim millions
from the construction costs for
Regatta’s second phase, which will create
115 condominiums in a new sevenstory
building next door to phase one.
For example, the co-developers
saved $1 million by using a slab foundation
instead of driving concrete pilings
into the wet ground beneath the waterfront
project. They saved $600,000 on
the $3 million cost of the building’s
floor-to-ceiling windows by including
vertical partitions that will allow the
glass pane to be thinner and still support
itself. Costs dropped another
$400,000 after the developers figured
out that condominiums with north-facing
windows could get away with
smaller air conditioning units and still
stay cool in the summer.
The changes will save the project
money without sacrificing the value that
the building will offer to its residents,
according to Fernando Levy Hara, new
projects and marketing manager for
G&D. Levy Hara contrasts this kind of
“value engineering” with simply downgrading
finishes: “Changing marble to
Italian tile? This is not value engineering,”
he said. “The buyer will pay less.”
In some cases, the co-developers
decided to spend more to add the right
kind of value to the project. For example,
it cost an extra $1 million to incorporate
the façade of a historic building
on the site, the Queen Elizabeth
Apartment Hotel, into the design of
Regatta’s second phase.
The work of preparing the site has
begun. In October, the developers
closed a $35 million construction loan
from Ohio Savings Bank to help pay for
the $57 million project. Developer equity
will provide the remaining project
cost.
Regatta 2 won’t be finished until
March 2010, giving the co-developers
more than two years to sell the condos
at prices now starting at $270,000 for a
651-square-foot studio and rising to $1.6
million for a penthouse suite.
|